6-8 Hanover Quay 26 January 2015

Bennett Construction Ltd appointed HDL in December 2014 to complete the following scope of works to this building:

Erect temporary propping to external walls for façade retention system.
Carefully remove asbestos roof sheeting and dispose to licensed facility.
Demolish internal structures to building including floors, stairs, walls, columns ad roof trusses. Provide temporary weathering to adjoining party wall, substructure excavation for new piled foundations, internal drainage and connections.