18-21 Charlemont Place 

The overall works package comprised of the demolition of 4-5 Storey Office Building and site clearance works at 18 – 21 Charlemont Place, Dublin. 

The site was bounded by an existing LUAS railine leading onto the Viaduct crossing at Charlemont Place. 

Works were as follows.  

  • Attending meetings with RPA/ARUP and preparing detailed methodologies for the part deconstruction and demolition of 5 storey structure directly adjacent to Viaduct and rail line. 
  • Preparation of Dilapidation surveys for surrounding structures and areas. 
  • Installation of noise, dust and vibration monitoring for the duration of demolition works on site. 
  • Carry out full Utilities review and engage utilities companies to disconnect all live services. 
  • Sterilise the site and remove all contaminated material. 
  • Stripping out and removal of all internal soft furnishing, fixtures. 
  • Stripping out and removal of all Mechanical and Electrical Plant & Equipment 
  • Demolition of  complete 4-5 Storey building over semi basement comprising of reinforced concrete frame with rib slab construction, walls, retaining walls, roof and plantroom. Approx. Area of 1,600 m2 
  • Erection of Protective self-supporting ballast scaffolding along the LUAS line for the duration of demolition works. 
  • Design proprietary propping system to backprob slabs/beams and columns to be saw cut and lifted as part of the deconstruct methodology agreed with the RPA.  
  • Demolish remaining structure mechanically and segregate arising on site.

Comments are closed.